title: Create a labour report
summary: Record the workers a contractor put on site, edit the record later, or delete it.
order: 1
menu: Site Reports > Labour Records
route: /labourchallans/make
who: People who have the Add Labour Records permission. Editing needs Edit and deleting needs Delete.
---

Use this form to record the labour that a contractor put on site. The date of the record is the day you create it. After you save, the record is **Pending** until an approver accepts it.

## Before you start

- The contractor (the **Vendor** on the form) and the labour type (the **Resource**) must exist in Superwise.
- If the labour type must be bought on a purchase order (PO), the PO must be approved and not closed.

## How to create a labour report

1. Open **Site Reports > Labour Records**.
2. Click **Create**. The form **Create/Edit Labour Report** opens for the project that is chosen at the top of the screen.
3. In **Vendor** (mark 1 in the first picture below), choose the contractor. Contractors that are not active show the word **Inactive**.
4. In **Resource** (mark 2), choose the labour type. The box is empty until you choose the vendor.
5. If a field **Purchase Order** appears, choose the PO. When the PO has revisions, a field **Purchase Order Revision** also appears.
6. In **Quantity** (mark 3), type the number of workers or units. The unit is shown next to the box.
7. In **Reference No.** (mark 4), type the contractor's slip number. You can type up to 20 characters.
8. In **Notes** (mark 1 in the second picture below), write what the workers did. In **Comments** (mark 2), write a comment for the approver. Each box takes up to 500 characters.
9. In **Images**, click **Select** (mark 3) and choose a picture of the workers.
10. Click **Save** (mark 5 in the first picture).

![The form to create a labour report. Marks 1 to 4 are the fields Vendor, Resource, Quantity and Reference No. Mark 5 is the Save button.](../media/labour-report-form.png)

![The section Notes and images. Mark 1 is Notes, mark 2 is Comments and mark 3 is the Select button for the picture.](../media/labour-report-form-notes.png)

The box **Summary** at the right shows the quantity. If a required field is empty, the box lists the problems. **Save** works when no problem is left.

## How to edit a labour report

1. In the list, click the pencil icon at the end of the row. You can also open the details and click **Edit**.
2. Change the fields. The vendor and the resource cannot be changed.
3. Click **Save**.

The pencil icon is not shown when the record is on a bill, or when its purchase order is closed.

## How to delete a labour report

1. In the list, click the bin icon at the end of the row.
2. In the dialog **Confirm Action**, click **Confirm**.
3. The message **Labour challan successfully deleted!** appears.

The bin icon is shown for **Pending** and **Rejected** records. It is also shown for **Accepted** records whose purchase order is open.

## What the fields mean

| Name | What it means |
| --- | --- |
| **Vendor** | The contractor who supplied the workers. You must choose one. |
| **Resource** | The labour type, for example mason. You must choose one. |
| **Purchase Order** | The PO that the record belongs to. Some labour types must have one. |
| **Purchase Order Revision** | The revision of the PO, when the PO was revised. |
| **Quantity** | The number of workers or units. It must be between 0.0001 and 100000000. |
| **Rate** | The price of one unit. It is shown when a PO is chosen. |
| **Reference No.** | The contractor's own slip number. |
| **Notes** | A note about the work done. |
| **Previous Comments** | The earlier comments on the record. They are shown after the first save. |
| **Comments** | Your new comment. |
| **Images** | A picture of the workers. Some labour types must have one. |

## Rules to know

- The quantity of all records on a PO line cannot be more than the stop quantity of that line.
- A labour type can be set to need a picture. Then you cannot save without one, and a star shows next to **Images**.
- A labour type can be set to need a PO. Then you cannot save without one.
- You cannot edit a record that is on a bill.

## If something goes wrong

| What you see | What to do |
| --- | --- |
| **Vendor is required** | Choose the contractor in **Vendor**. |
| **Quantity is required** | Type the quantity. |
| **Purchase Order is Required for Resource.** | Choose a PO in **Purchase Order**. |
| **The Labour Challan Quantity you have entered exceeds the PO order quantity** | Lower the quantity, or ask the buyer to change the PO. |
| **Challan is Required.** | Type the contractor's slip number in **Reference No.**. |
| **Labour Challan has already been billed. Please rectify the bill and try deleting again.** | Change the bill first, then delete the record. |
