title: Revisions
summary: Compare a changed schedule with the live one, send it for approval, and approve or reject it. Each approval makes a new revision.
order: 6
menu: Planning > Schedule
route: /scheduleplayground
who: People who have the View Tasks permission. Asking for approval needs Add or Edit. Approving and rejecting need Approve.
---

A revision is one approved version of the schedule. When you change the plan in the [Playground](playground.md) or by file, the change is a draft. The draft becomes live only after someone with the approval right accepts it. Each approval makes a new revision with a new number.

The **Revisions** screen lists all revisions and the current draft. The **Compare** screen shows what the draft changes and is where you ask for approval.

![The Revisions list. Mark 1 is the search box and mark 2 is the Revision column.](../media/schedule-revisions-list.png)

## Before you start

- A draft must exist. Save the draft in the playground, verify it, and use **Save Tasks**. See [Create a schedule](create-schedule.md).
- You can ask for approval only after the tasks are updated. Before that, the **Final Schedule** tab says "Tasks need to be updated before viewing the Final Schedule."

## How to see the revisions

1. Open **Schedule > Tasks**, click **More actions** and choose **Playground Revisions**. To go to the Compare screen directly, click **Compare** at the top of the Tasks screen or of the playground.
2. The list shows each revision with **Revision**, **Start Date**, **Completion Date**, **Duration**, **Status Changed On** and **Status Changed By**.
3. The current live revision shows `(Current Version)` after its number and has a green row. A draft shows **Draft Version** and has a pale yellow row.
4. Click the arrow in front of a row to open its details. The tab **Details** shows who created and changed the revision and the remarks. The tab **Attachments** has a **Download** button for each file that came with the request.
5. To search, type at least 3 characters in the search box.
6. For a draft row, click the three dots and choose **Summary** to open the Compare screen. An approver sees **Approve/Reject** instead.

## How to compare a draft with the live schedule

1. Open the Compare screen. The title shows **Compare** and a pill with the revision number.
2. Read the tabs one by one.
   - **Final Schedule** shows the new tree with **Name**, **Act/Exp Duration**, **Act/Exp Start**, **Act/Exp Finish** and **Status**.
   - **Blockers** lists deleted tasks that still have BOQs.
   - **Changed Links**, **Changed Nodes**, **Changed Templates**, **Changed Template Variations** and **Changed Resource Planning** list what changed in each part of the plan.
3. In every table, a **Status** says **Added**, **Deleted**, **Modified** or **Unchanged**. **Added** is green, **Deleted** is red and **Modified** is orange. A changed value shows the old value struck out and the new value after it.
4. A line above the table counts the changed tasks and areas, for example "5 task(s) changed, 120 unchanged".

![The Compare screen. The tabs from Final Schedule to Changed Resource Planning show every kind of change.](../media/schedule-compare.png)

## How to ask for approval

1. On the Compare screen, click **Request Approval**. The button shows only when the tasks are updated and you have the Add or Edit permission.
2. In the window **Request Approval**, write the **Remarks (compulsory)**.
3. If you have a file for the approver, add it with the upload box. For example, add a PDF of the new plan.
4. Tick the box **Playgound Changes affect Cost** if the change affects cost. The estimation team then gets a notice after approval.
5. Click **Confirm**. **Confirm** works only when the remarks are filled.
6. Superwise says: "Approval request has been sent. We will inform you once the approval is complete."

## How to approve or reject

You need the Approve permission. The buttons show when the request is waiting.

1. Open the Compare screen.
2. Read the **Last Request** line. It shows who asked and when.
3. Click **Approve** or **Reject**.
4. In the window **Confirm Approval**, the remarks are optional. In **Confirm Rejection**, the remarks are compulsory.
5. Click **Confirm**. Superwise says "Schedule has been approved!" or "Schedule has been rejected!".

## How to throw away the draft

1. On the Compare screen, click **Revert All Changes**.
2. Type `RESET` in the box and click **Confirm**.
3. Superwise says "Schedule and BOQ Playground changes have been reverted!".

The button shows only for the people who can add or edit, and only when the project already has an approved revision.

## Rules to know

- Approval is not possible while a deleted task still has a BOQ. Superwise says so and the **Blockers** tab lists the tasks. Ask the cost team to remove the BOQs.
- When you approve, Superwise deletes these records of the deleted tasks: submitted checklists, issues, labour utilization entries, material receipts and task progress.
- Each approval makes a new baseline. See [Baselines](baselines.md).

> **Careful:** Approval deletes the progress, issues and receipts of tasks that the new plan removes. Read the **Final Schedule** tab before you approve.

## If something goes wrong

| What you see | What to do |
| --- | --- |
| Approval is not possible because deleted Tasks have BOQs. | Ask the cost team to remove the BOQs from those tasks. They are listed in **Blockers**. |
| **Request Approval** is missing | The tasks are not updated yet, or you do not have the Add or Edit permission. |
| **Confirm** is grey | Write the remarks. |
| **Approve** and **Reject** are missing | No request is waiting, or you do not have the Approve permission. |
