Request a payment
Ask for a payment for a bill, an RA bill, a purchase order advance, a work order advance, a retention or a cash advance, and change or send back a request.
- Where to find it
- Accounts > Payments > All Payments
- Who can use it
- People who have the Add Payments permission. Editing a request needs Edit.
You make a payment request to start the payment of a bill or an advance. The request then goes to the director and to accounts for approval. See Payments for the whole flow.
For example, Acme owes Alder Steel Works ₹1,00,000 for a certified bill. You open a new request, choose Bill Payment, choose the supplier and the bill, and Superwise fills the amount.
Before you start
- Select the project at the top of the screen.
- For Bill Payment, certify the purchase bill first.
- For RA Bill Payment, the RA bill must be Accepted.
- You need the Add permission on Payments.
How to request a payment
- Open Accounts in the left menu, open Payments and click All Payments.
- Click Create New Request.
- Check Project. Change it if the request is for another project.
- In Payment For, choose the kind of payment. The next fields depend on this choice. See the table below.
- Choose the person or the company, and the bill, voucher, order or RA bill. See the table below.
- Check Requested Amount. Superwise fills it from the bill, the vouchers or the RA bill. You can change it.
- In Payment By, choose the date by which the money should be paid.
- In Preferred Mode, choose Cash, Cheque, BankTransfer or PDC. PDC is a post-dated cheque.
- In Notes, type a message for the approvers.
- Click Create. For RA Bill Payment the button says Process.
What to fill for each kind of payment
| Payment For | What to choose | What the amount is |
|---|---|---|
| PO Advance | Organization, then Purchase Order | You type it. |
| Bill Payment | Organization, then one or more Bills | The pending amount of the bills. |
| Advance Cash | Paid To, a person on site | You type it. |
| Reimburse Cash Expense | Paid To, then Expense Vouchers | The total of the vouchers. |
| Work Order Advance | Organization | You type it. |
| RA Bill Payment | Organization, then RA Bill | The pending amount of the RA bill. |
| Retention Payment | Organization | You type it. |
Under the form, tabs show what was already paid and what is still open for that supplier or person. For a bill payment the tabs are Bills Accepted, Payment Processed, Bills Pending and Payments Unprocessed. Use them to avoid paying twice.
How to change a request
- In All Payments, click the Edit button at the end of the row.
- Change the fields. The button says Save.
- Click Save. The request goes back to Queued. The approvers decide again.
What the fields mean
| Name | What it means |
|---|---|
| Project | The project that pays. |
| Payment For | The kind of payment. |
| Paid To | The person who gets cash. |
| Organization | The supplier or contractor who gets the money. |
| Purchase Order | The order that the advance is for. |
| Bills | The certified bills that you want to pay. |
| Expense Vouchers | The cash expense vouchers that you reimburse. |
| RA Bill | The RA bill that you pay. |
| Requested Amount | The amount you ask for. |
| Payment By | The date by which the money should be paid. |
| Preferred Mode | The way you prefer to pay. The accountant can choose another when releasing. |
| Notes | A message that the approvers and the accountant read. |
Rules to know
- A bill can be in one request only. Superwise shows Payment requests already created for Bill No for a second request.
- An advance needs a purchase order. Superwise shows No PO Mentioned for Advance Payment if it is empty.
- An RA bill payment needs an RA bill. Superwise shows No RA Bill selected for Payment if it is empty.
- A cash reimbursement needs vouchers, and each voucher must be accepted. Superwise shows No Expenses Added or the status of the voucher otherwise.
- A request for RA Bill Payment is processed at once. It does not wait for approval.
If something goes wrong
| What you see | What to do |
|---|---|
| Access denied | You do not have the Add permission on Payments. |
| No Bill Details Added | Choose at least one bill in Bills. |
| Payment requests already created for Bill No | The bill already has a request. Edit or delete that request instead. |